Test your Scrum framework knowledge now with our first free Exam PSM I Simulator!
Time limit: 0
Quiz-summary
0 of 80 questions completed
Questions:
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
Information
Number of questions: 80 Time Limit: 60 minutes Passing score: 85%
You can navigate through the questions whenever you want. The unanswered questions are marked in the navigation system. You can click the “review question” button to flag it for later review.
When you’re done answering the questions, click on the Quiz Summary button, then on Finish Quiz. You will see your score, and you can click on the View Questions button to receive feedback on all questions.
Click “Start quiz” when you are ready to begin.
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Results
0 of 80 questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 points, (0)
Average score
Your score
Categories
Not categorized0%
Your result has been entered into leaderboard
Loading
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
Answered
Review
Question 1 of 80
1. Question
1 points
What should be the duration of a Sprint?
Correct
All these choices are correct criteria in deciding the duration of a Sprint.
Incorrect
All these choices are the correct criteria for deciding the duration of a Sprint.
Question 2 of 80
2. Question
1 points
What’s the main responsibility of the Project Manager?
Correct
We have only just three roles in Scrum: Product Owner , Scrum Master , and Development Team . It’s not permitted to define new roles and the Development Team must be self-organizing and cross-functional.
Incorrect
We have only just three roles in Scrum: Product Owner , Scrum Master , and Development Team . It’s not permitted to define new roles and the Development Team must be self-organizing and cross-functional.
Question 3 of 80
3. Question
1 points
When is a backlog item considered complete?
Correct
When the item is complete based on the Definition of Done, therefore the real and final users can use it, which also means an Increment of working software which is potentially releasable has been created.
Incorrect
When the item is complete based on the Definition of Done, therefore the real and final users can use it, which also means an Increment of working software which is potentially releasable has been created.
Question 4 of 80
4. Question
1 points
Which three things are Scrum Master responsibilities during the Sprint?
Correct
The Scrum Master is responsible for helping everyone understand Scrum theory, practices, rules, and values. Removes impediments (solves problems), facilitates the meetings as needed. The whole Scrum Team decides the Sprint length considering one month for the maximum duration. Tasks are assigned by the Developers themselves.
Incorrect
The Scrum Master is responsible for helping everyone understand Scrum theory, practices, rules, and values. Removes impediments (solves problems), facilitates the meetings as needed. The whole Scrum Team decides the Sprint length considering one month for the maximum duration. Tasks are assigned by the Developers themselves.
Question 5 of 80
5. Question
1 points
Is one of the Scrum Theory Pillars
Correct
Adaptation, Transparency, and Inspection are the Scrum Theory Pillars. Scrum as Agile framework, is mainly about adaptation (instead of prediction).
Incorrect
Adaptation, Transparency, and Inspection are the Scrum Theory Pillars. Scrum as Agile framework, is mainly about adaptation (instead of prediction).
Question 6 of 80
6. Question
1 points
Which three of the following are true about the Scrum Master role?
Correct
Despite the Scrum Master doesn’t manage people, he manages processes. That’s why it’s considered a management role. The Development Team is self-organized; the Scrum Master can coach and help but the developers are who handle the progress and performance of the Sprints. It is the Product Owner who owns the Product Backlog.
Incorrect
Despite the Scrum Master doesn’t manage people, he manages processes. That’s why it’s considered a management role. The Development Team is self-organized; the Scrum Master can coach and help but the developers are who handle the progress and performance of the Sprints. It is the Product Owner who owns the Product Backlog.
Question 7 of 80
7. Question
1 points
Who must do the work required for Product Backlog items, in order to create a potentially releasable Increment?
Correct
The Development Team is cross-functional and does the work of delivering a potentially releasable Increment of “Done” product at the end of each Sprint. They don’t use any external help. Is not recommended, nor is a good practice, for the Scrum Master or Product Owner working as developers.
Incorrect
The Development Team is cross-functional and does the work of delivering a potentially releasable Increment of “Done” product at the end of each Sprint. They don’t use any external help. Is not recommended, nor is a good practice, for the Scrum Master or Product Owner working as developers.
Question 8 of 80
8. Question
1 points
What is the right criteria to order the Product Backlog?
Correct
The decision on the order of items can be influenced by a committee, the customer, or any other stakeholder, but only the Product Owner decides what makes the most sense to optimize the value of the work being done by the Development Team.
Incorrect
The decision on the order of items can be influenced by a committee, the customer, or any other stakeholder, but only the Product Owner decides what makes the most sense to optimize the value of the work being done by the Development Team.
Question 9 of 80
9. Question
1 points
Who estimates the work during the Sprint?
Correct
Since people who actually do the work are the ones who best know what is needed to complete specific tasks; all estimates are done by the Development Team.
Incorrect
Since people who actually do the work are the ones who best know what is needed to complete specific tasks; all estimates are done by the Development Team.
Question 10 of 80
10. Question
1 points
Which are two good approaches for the Development Team to make non-functional requirements visible?
Correct
The Product Owner is the sole person responsible for managing the Product Backlog but always can and must consider the feedback and opinion from other stakeholders including the Development Team who can influence to add new items in Product Backlog. Good requirements should be brieg enough, that’s why acceptance tests can be used to express many of the details that result from the conversations between customers, users, Product Owners and developers, including non-functional requirements. One product only has one Product Backlog.
Incorrect
The Product Owner is the sole person responsible for managing the Product Backlog but always can and must consider the feedback and opinion from other stakeholders including the Development Team who can influence to add new items in Product Backlog. Good requirements should be brieg enough, that’s why acceptance tests can be used to express many of the details that result from the conversations between customers, users, Product Owners and developers, including non-functional requirements. One product only has one Product Backlog.
Question 11 of 80
11. Question
1 points
Which are two reason Scrum promotes self-organized teams?
Correct
Being self-organized implies that the team follows its very own process, rather than receiving orders. When it’s so, the members of the team tend to commit themselves and increase their accountability, and creativity.
Incorrect
Being self-organized implies that the team follows its very own process, rather than receiving orders. When it’s so, the members of the team tend to commit themselves and increase their accountability, and creativity.
Question 12 of 80
12. Question
1 points
Hardening Sprints are needed every few Sprints, to resolve dependencies and reduce technical debt.
Correct
There’s no hardening Sprint, Sprint zero, integration Sprint, release Sprint, etc. There’s just one type of Sprint, and its goal is to create an Increment of potentially releasable valuable features.
Incorrect
There’s no hardening Sprint, Sprint zero, integration Sprint, release Sprint, etc. There’s just one type of Sprint, and its goal is to create an Increment of potentially releasable valuable features.
Question 13 of 80
13. Question
1 points
Who’s responsible for communicating and engaging the stakeholders?
Correct
Product Owners should communicate effectively with the customers therefore also engaging them.
Incorrect
Product Owners should communicate effectively with the customers therefore also engaging them.
Question 14 of 80
14. Question
1 points
When can the composition of the Development Team change?
Correct
This shouldn’t be often because it creates a short time reduction in the productivity, but if needed, try to avoid team members changes during the Sprint.
Incorrect
This shouldn’t be often because it creates a short time reduction in the productivity, but if needed, try to avoid team members changes during the Sprint.
Question 15 of 80
15. Question
1 points
What is what usually happens when the Scrum Team becomes mature through the project? (two answers)
Correct
Every team tends to learn more and mature during the project, so the techniques, expertise, skills and methods improve too. This must impact on the definition of Done.
All Scrum roles, events, and artifacts are necessary and shouldn’t be omitted for any reason.
Incorrect
Every team tends to learn more and mature during the project, so the techniques, expertise, skills and methods improve too. This must impact on the definition of Done.
All Scrum roles, events, and artifacts are necessary and shouldn’t be omitted for any reason.
Question 16 of 80
16. Question
1 points
Which of the following is not a Development Team responsibility?
Correct
Remember that Development Team is self-organized. Therefore, It is team’ responsibility to measure its own productivity and performance throughout the Sprint, figure out its own process, plan, estimate and optimize the work required for items and the Sprint Goal, and to resolve their own conflicts.
Incorrect
Remember that Development Team is self-organized. Therefore, It is team’ responsibility to measure its own productivity and performance throughout the Sprint, figure out its own process, plan, estimate and optimize the work required for items and the Sprint Goal, and to resolve their own conflicts.
Question 17 of 80
17. Question
1 points
The CTO of your organization and one of the most important clients ask some members of the Development Team to add a new feature in the middle of the Sprint. What should they do?
Correct
One the main responsibilities of the Product Owner is to maximize the value of the Development Team’s work, and he’s the only one who can add new items to the Product Backlog. Even when the Development Team owns the Sprint Backlog, the members don’t add items arbitrarily, the Product Owner must make sure that any new item adds value and she or he can work with proper stakeholders about it and then add it to the Product Backlog for the next Sprints. Also, the Product Owner can reject the new feature, rather than the Development Team.
Incorrect
One the main responsibilities of the Product Owner is to maximize the value of the Development Team’s work, and he’s the only one who can add new items to the Product Backlog. Even when the Development Team owns the Sprint Backlog, the members don’t add items arbitrarily, the Product Owner must make sure that any new item adds value and she or he can work with proper stakeholders about it and then add it to the Product Backlog for the next Sprints. Also, the Product Owner can reject the new feature, rather than the Development Team.
Question 18 of 80
18. Question
1 points
When can a Development Team cancel a Sprint?
Correct
The only one who can cancel a Sprint is the Product Owner. This can happen when he realizes that the Sprint doesn’t make sense anymore, because the Sprint Goal has become obsolete.
Incorrect
The only one who can cancel a Sprint is the Product Owner. This can happen when he realizes that the Sprint doesn’t make sense anymore, because the Sprint Goal has become obsolete.
Question 19 of 80
19. Question
1 points
What amount of work should the Development Team do to a selected Product Backlog item to complete the Sprint?
Correct
The agreed definition of “Done” for the Scrum Team, is used to assess when work is complete on the product Increment in order to deliver an Increments of potentially releasable functionality.
Incorrect
The agreed definition of “Done” for the Scrum Team, is used to assess when work is complete on the product Increment in order to deliver an Increments of potentially releasable functionality.
Question 20 of 80
20. Question
1 points
When should the Scrum Team held the Sprint Retrospective meeting?
Correct
The Sprint Retrospective occurs always after the Sprint Review and prior to the next Sprint Planning.
Incorrect
The Sprint Retrospective occurs always after the Sprint Review and prior to the next Sprint Planning.
Question 21 of 80
21. Question
1 points
What is an output of a Sprint?
Correct
The purpose of the Sprints is creating increments; in other words, a piece of working product which is potentially shippable and based on the agreed Definition of “Done”, regardless of the techniques, documents or methods used to achieve this.
Incorrect
The purpose of the Sprints is creating increments; in other words, a piece of working product which is potentially shippable and based on the agreed Definition of “Done”, regardless of the techniques, documents or methods used to achieve this.
Question 22 of 80
22. Question
1 points
The structure of the Daily Scrum is set by the Development Team.
Correct
The Development Team owns the Daily Scrum meetings, they can be conducted in different ways but always focuses on progress toward the Sprint Goal.
Incorrect
The Development Team owns the Daily Scrum meetings, they can be conducted in different ways but always focuses on progress toward the Sprint Goal.
Question 23 of 80
23. Question
1 points
Who must attend to the Daily Scrum?
Correct
The only ones who must attend are the members of the Scrum Team. The Scrum Master ensures that the Development Team has the meeting but he doesn’t need to be present at the meeting. Anyone else can attend but don’t “must” be there, and notice that the guests only watch and listen they don’t participate.
Incorrect
The only ones who must attend are the members of the Scrum Team. The Scrum Master ensures that the Development Team has the meeting but he doesn’t need to be present at the meeting. Anyone else can attend but don’t “must” be there, and notice that the guests only watch and listen they don’t participate.
Question 24 of 80
24. Question
1 points
Each Sprint Backlog item is owned by one or more developers.
Correct
The whole Developer Teams share the Sprint Backlog items ownership and their tasks; these tasks assigned to the Developers by themselves. Also, all members of the Developer Team share the accountability of their own tasks.
Incorrect
The whole Developer Teams share the Sprint Backlog items ownership and their tasks; these tasks assigned to the Developers by themselves. Also, all members of the Developer Team share the accountability of their own tasks.
Question 25 of 80
25. Question
1 points
When we have more risk we need lonker Sprints.
Correct
When we have shorter Sprints, there are more opportunities to show progress, and receive feedback, validate our knowledge and therefore Adapt. So, shorter Sprints are preferred when we have higher risks.
Incorrect
When we have shorter Sprints, there are more opportunities to show progress, and receive feedback, validate our knowledge and therefore Adapt. So, shorter Sprints are preferred when we have higher risks.
Question 26 of 80
26. Question
1 points
Always must be a Release after each Sprint.
Correct
The main purpose of the Sprint is to create an increment of useable, and potentially releasable “Done” product.
Incorrect
The main purpose of the Sprint is to create an increment of useable, and potentially releasable “Done” product.
Question 27 of 80
27. Question
1 points
Which are three responsibilities of a self-organizing team?
Correct
It’s the responsibility of the Development Team to select the appropriate number of Product Backlog items, break down the tasks and create estimations for them each Sprint.
Incorrect
It’s the responsibility of the Development Team to select the appropriate number of Product Backlog items, break down the tasks and create estimations for them each Sprint.
Question 28 of 80
28. Question
1 points
Who knows the most about the project’s performance?
Correct
The Product Owner is responsible for measuring project performance. The Development Team only measures the performance of the current Sprint.
Incorrect
The Product Owner is responsible for measuring project performance. The Development Team only measures the performance of the current Sprint.
Question 29 of 80
29. Question
1 points
The Product Owner decides how many Product Backlog items should be selected for next Sprint.
Correct
The Product Owner sets the objective that the Sprint should achieve although can be influenced by the Development Team. However, only members of the Development Team create the Increment, that’s why only they pull the Product Backlog items in order to accomplish Sprint Goal.
Incorrect
The Product Owner sets the objective that the Sprint should achieve although can be influenced by the Development Team. However, only members of the Development Team create the Increment, that’s why only they pull the Product Backlog items in order to accomplish Sprint Goal.
Question 30 of 80
30. Question
1 points
The Development Team and the Product Owner are not working together at all. What should the Scrum Master do?
Correct
The Scrum Master must coach the whole Scrum Team members in organizational environments in which Scrum is not yet fully adopted and understood to practice agility. The Scrum Master must help them to effectively communicate each other, but be careful, don’t act as a go-between for them.
Incorrect
The Scrum Master must coach the whole Scrum Team members in organizational environments in which Scrum is not yet fully adopted and understood to practice agility. The Scrum Master must help them to effectively communicate each other, but be careful, don’t act as a go-between for them.
Question 31 of 80
31. Question
1 points
During the Sprint Planning that is moving ahead, the Development Team has become aware they won’t be able to finish the work for all selected Sprint Backlog items. Which two of the following are usually the best actions?
Correct
Even if the team doesn’t deliver increment the Product Owner must be informed about it, and s/he must work with the Development Team and adjust, add, and/or remove Sprint Backlog Items thoroug the Sprint in order to achieve the Sprint Goal. But, since this is still the Sprint Planning we also still have the chance to modify de Sprint Goal, we won’t able to do so after the Sprint Planning.
We always work on a regular and constant pace, we shouldn’t work overtime.
We shouldn’t change the number of developers, adding developers won’t increase productivity in short term.
Incorrect
Even if the team doesn’t deliver increment the Product Owner must be informed about it, and s/he must work with the Development Team and adjust, add, and/or remove Sprint Backlog Items thoroug the Sprint in order to achieve the Sprint Goal. But, since this is still the Sprint Planning we also still have the chance to modify de Sprint Goal, we won’t able to do so after the Sprint Planning.
We always work on a regular and constant pace, we shouldn’t work overtime.
We shouldn’t change the number of developers, adding developers won’t increase productivity in short term.
Question 32 of 80
32. Question
1 points
Which two answers are true about the Definition of “Done”?
Correct
The Definition of “Done” defines what is expected as result of the current Sprint. This include (but not limited) to acceptance criteria and non-functional features. The purpose is to share the same understanding of the completed work to increase transparency.
The Sprint Goal is what defines the purpose of the Sprint.
The Development Team must have present that the Definition of “Done” to create tasks, but also the description of each pulled Product Backlog items.
Incorrect
The Definition of “Done” defines what is expected as result of the current Sprint. This include (but not limited) to acceptance criteria and non-functional features. The purpose is to share the same understanding of the completed work to increase transparency.
The Sprint Goal is what defines the purpose of the Sprint.
The Development Team must have present that the Definition of “Done” to create tasks, but also the description of each pulled Product Backlog items.
Question 33 of 80
33. Question
1 points
Which are three reasons why to include tests in the Definition of “Done” is a good practice?
Correct
We need to know when an item is really Done, in other words, we share a common understanding of what means a finished job. With this purpose, we can increase Transparency when there are tests included in the Definition of “Done”, which will verify how close is the work of being “complete”, “potentially releasable” and becoming a real Increment usable for final users.
Also writing acceptance tests help to express many of the details that result from the conversations between customers and Scrum Teams, rather than writing long lists of “The system shall…”.
Incorrect
We need to know when an item is really Done, in other words, we share a common understanding of what means a finished job. With this purpose, we can increase Transparency when there are tests included in the Definition of “Done”, which will verify how close is the work of being “complete”, “potentially releasable” and becoming a real Increment usable for final users.
Also writing acceptance tests help to express many of the details that result from the conversations between customers and Scrum Teams, rather than writing long lists of “The system shall…”.
Question 34 of 80
34. Question
1 points
Who can decide add more work to the Sprint Backlog during the Sprint?
Correct
After de Sprint Planning the items pulled from Sprint Backlog can’t be changed. But the broken down tasks created by de Development Team to complete the work are always changing and adapting according to their practices, techniques, and knowledge.
Incorrect
After de Sprint Planning the items pulled from Sprint Backlog can’t be changed. But the broken down tasks created by de Development Team to complete the work are always changing and adapting according to their practices, techniques, and knowledge.
Question 35 of 80
35. Question
1 points
During the Sprint the Development Team determines that cannot complete its work by the end of the Sprint. What happens in this case?
Correct
Multiple Scrum Teams should use the definition of “Ready” to normalize estimations. This way it will be easier to measure and compare their performance
Incorrect
Multiple Scrum Teams should use the definition of “Ready” to normalize estimations. This way it will be easier to measure and compare their performance
Question 36 of 80
36. Question
1 points
Multiple Scrum Teams should use the definition of “Ready” to normalize estimations. This way it will be easier to measure and compare their performance
Correct
There are no comparable estimation units between the Development Teams, each team is different. If you try to normalize, you can lead to misunderstandings and padding problems.
Definition of “Ready” is a common practice but is not part of the Scrum guide, and its purpose is neither to normalize estimations nor performance measuring.
Incorrect
There are no comparable estimation units between the Development Teams, each team is different. If you try to normalize, you can lead to misunderstandings and padding problems.
Definition of “Ready” is a common practice but is not part of the Scrum guide, and its purpose is neither to normalize estimations nor performance measuring.
Question 37 of 80
37. Question
1 points
Which two statements are true about the Product Owner?
Correct
The Product Owner is responsible for maximizing the value of the product resulting from work of the Development Team and prioritize the Product Backlog items accordingly.
There is no role of Project Manager or equivalent in the Scrum framework.
Product Owner can be dedicated part-time to one project.
Incorrect
The Product Owner is responsible for maximizing the value of the product resulting from work of the Development Team and prioritize the Product Backlog items accordingly.
There is no role of Project Manager or equivalent in the Scrum framework.
Product Owner can be dedicated part-time to one project.
Question 38 of 80
38. Question
1 points
Eventually, the Scrum Master becomes unnecessary when the Development Team matures through the project.
Correct
If a project does not include Scrum Master or Product Owner roles, this project is not doing Scrum. Both roles can be part-time but always are performed in a Scrum project. One of the must important Scrum Master activities is removing impediments, and it doesn’t matter how mature is the Development Team, its members will be always benefited when someone takes care of these issues.
Incorrect
If a project does not include Scrum Master or Product Owner roles, this project is not doing Scrum. Both roles can be part-time but always are performed in a Scrum project. One of the must important Scrum Master activities is removing impediments, and it doesn’t matter how mature is the Development Team, its members will be always benefited when someone takes care of these issues.
Question 39 of 80
39. Question
1 points
How much of the Sprint Backlog needs to be defined throughout the Sprint Planning meeting?
Correct
Scrum does not do upfront planning, only a few tasks broken down from the items are created in the Sprint Planning.
The Development Team is self-organized, their members decide who does what.
There is no baseline for a Scrum project.
Incorrect
Scrum does not do upfront planning, only a few tasks broken down from the items are created in the Sprint Planning.
The Development Team is self-organized, their members decide who does what.
There is no baseline for a Scrum project.
Question 40 of 80
40. Question
1 points
What is the most important subject that the Scrum Team should resolve during Sprint zero?
Correct
There’s no such thing as Sprint zero. The first Sprint is the first one, and it’s not different from other Sprints, from the perspective that the Developer Team should create an Increment. The infrastructure, tools and requirements are prepared gradually throughout the project.
Incorrect
There’s no such thing as Sprint zero. The first Sprint is the first one, and it’s not different from other Sprints, from the perspective that the Developer Team should create an Increment. The infrastructure, tools and requirements are prepared gradually throughout the project.
Question 41 of 80
41. Question
1 points
41. The Development Team should prepare a complete infrastructure and set of tools for the project during the first Sprint
Correct
The Development Team neither analyze, design nor describe the complete architecture and infrastructure, beforehand for the whole project. Agile processes are characterized by frequent short bursts of design, just enough to reach the Sprint Goal.
Incorrect
The Development Team neither analyze, design nor describe the complete architecture and infrastructure, beforehand for the whole project. Agile processes are characterized by frequent short bursts of design, just enough to reach the Sprint Goal.
Question 42 of 80
42. Question
1 points
Who can remove and replace Sprint Backlog items during the Sprint?
Correct
No one can remove or change the Sprint Backlog items when the Sprint Planning is finished. The only exception is when there’s still time and the team has completed all items, in which scenario they will pull the next item from the top of the Product Backlog.
Incorrect
No one can remove or change the Sprint Backlog items when the Sprint Planning is finished. The only exception is when there’s still time and the team has completed all items, in which scenario they will pull the next item from the top of the Product Backlog.
Question 43 of 80
43. Question
1 points
Which two of the following is true about Scrum?
Correct
Scrum is not a methodology or body of knowledge, is a framework. A lot of organizations start implementing Agile in a cultural context that is mostly non-Agile.This creates tensions and frictions that the teams adopting Agile have to deal with.
According to the Scrum Guide, a Sprint is a time-box of 4 weeks maximum (can be less).
Incorrect
Scrum is not a methodology or body of knowledge, is a framework. A lot of organizations start implementing Agile in a cultural context that is mostly non-Agile.This creates tensions and frictions that the teams adopting Agile have to deal with.
According to the Scrum Guide, a Sprint is a time-box of 4 weeks maximum (can be less).
Question 44 of 80
44. Question
1 points
Product Owner says the customer has security concerns. Where can be addressed these concerns in Scrum? (Select 2 answers).
Correct
Many nonfunctional features, like security, can be added as acceptance criteria and tests in the Definition of Done to be applied to all or some Product Backlog items.
We can have some specic security concerns that can be items in the Product Backlog.
The Development Team is crossfunctional and self-sufficient, should be capable of taking care of every aspect of the product, including security.
Incorrect
Many nonfunctional features, like security, can be added as acceptance criteria and tests in the Definition of Done to be applied to all or some Product Backlog items.
We can have some specic security concerns that can be items in the Product Backlog.
The Development Team is crossfunctional and self-sufficient, should be capable of taking care of every aspect of the product, including security.
Question 45 of 80
45. Question
1 points
Lower positioned, Product Backlog items, are usually larger and less clear than those on the top.
Correct
When Product Backlog is created, items are added to it. They have different sizes and eventually are ordered on their business value. The most valued items will be on the top and usually, these items would be broken down into smaller ones. We don’t do this with those items on the bottom. That’s why usually larger and less clear items are on the bottom of the Product Backlog.
Incorrect
When Product Backlog is created, items are added to it. They have different sizes and eventually are ordered on their business value. The most valued items will be on the top and usually, these items would be broken down into smaller ones. We don’t do this with those items on the bottom. That’s why usually larger and less clear items are on the bottom of the Product Backlog.
Question 46 of 80
46. Question
1 points
What is the proper way to ordering Product Backlog items?
Correct
The Product Backlog items are ordres accordenly based on their business value. The Product Owner is responsible for the Product Backlog, including its content, availability, and ordering. The Product Owner can consider items size and risk, but among others, these are only criteria to stablish final value. Items should be independant from each other, in order to facilitate their ordering.
Incorrect
The Product Backlog items are ordres accordenly based on their business value. The Product Owner is responsible for the Product Backlog, including its content, availability, and ordering. The Product Owner can consider items size and risk, but among others, these are only criteria to stablish final value. Items should be independant from each other, in order to facilitate their ordering.
Question 47 of 80
47. Question
1 points
Every increment should be released.
Correct
Every increment should be potentially releasable and completed based on the Definition of Done. However, increment doesn’t have to be actually released. The Product Owner decides if make sense to release or not.
Incorrect
Every increment should be potentially releasable and completed based on the Definition of Done. However, increment doesn’t have to be actually released. The Product Owner decides if make sense to release or not.
Question 48 of 80
48. Question
1 points
From the following options, what is the best way a Scrum Master can increase the team productivity?
Correct
Removing impediments and facilitating Scrum events as requested or needed is the kind of thing expected from the Scrum Master. The development team is self-organized; the Scrum Master does not give them orders. The Scrum Master must ensure that the Product Owner knows how to organize the Product Backlog to maximize value, but the Scrum Master is not responsible for doing it.
Incorrect
Removing impediments and facilitating Scrum events as requested or needed is the kind of thing expected from the Scrum Master. The development team is self-organized; the Scrum Master does not give them orders. The Scrum Master must ensure that the Product Owner knows how to organize the Product Backlog to maximize value, but the Scrum Master is not responsible for doing it.
Question 49 of 80
49. Question
1 points
The Product Owner wants to create estimations and ask the Scrum Master for guidance about it. What is the most proper guideline that the Scrum Master should give?
Correct
Only members of the Development Team create the Increment and are the best suited Scrum Team members to do estimations. The Product Owner and the Scrum Master can suggest and use techniques to help the development team to measure their effort, however, only the Development Team does the estimation itself.
Incorrect
Only members of the Development Team create the Increment and are the best suited Scrum Team members to do estimations. The Product Owner and the Scrum Master can suggest and use techniques to help the development team to measure their effort, however, only the Development Team does the estimation itself.
Question 50 of 80
50. Question
1 points
What two approaches should the Scrum Master take when your team doesn’t have the proper infrastructure to do the work needed to complete the selected Product Backlog items?
Correct
The infrastructure and tools are prepared gradually throughout the project, and the Sprint Goal and Definition of Done should be realistic and created accordingly.
Incorrect
The infrastructure and tools are prepared gradually throughout the project, and the Sprint Goal and Definition of Done should be realistic and created accordingly.
Question 51 of 80
51. Question
1 points
51. What is the best Scrum description?
Correct
Scrum is a framework which is adaptative and empirical rather than theoretical, thus it can be used for the development of complex products in complex environments. Scrum is more about project delivery than project management, therefore is neither a methodology nor body of knowledge.
Incorrect
Scrum is a framework which is adaptative and empirical rather than theoretical, thus it can be used for the development of complex products in complex environments. Scrum is more about project delivery than project management, therefore is neither a methodology nor body of knowledge.
Question 52 of 80
52. Question
1 points
You have several Scrum Teams working on the same product. Which is the best approach in order to carry the Sprint Planning?
Correct
– There’s only one Product Backlog and one Product Owner for one product. Each team needs to have a separate Sprint Backlog however.
– The Development Team is responsible for selecting the items from the Product Backlog, however, they can select representatives to do so. They share ownership on these though.
– Team members can change the composition of teams (shift) between Sprints.
– Even though Product Backlog items should be independent of each other, the dependencies between teams are unavoidable in scaled Scrum and they need to be handled.
Incorrect
– There’s only one Product Backlog and one Product Owner for one product. Each team needs to have a separate Sprint Backlog however.
– The Development Team is responsible for selecting the items from the Product Backlog, however, they can select representatives to do so. They share ownership on these though.
– Team members can change the composition of teams (shift) between Sprints.
– Even though Product Backlog items should be independent of each other, the dependencies between teams are unavoidable in scaled Scrum and they need to be handled.
Question 53 of 80
53. Question
1 points
Scrum is a methodology which describes detailed steps to get working software.
Correct
Scrum doesn’t describe any detailed step, and rather than a methodology is a framework.
Incorrect
Scrum doesn’t describe any detailed step, and rather than a methodology is a framework.
Question 54 of 80
54. Question
1 points
How should the members of multiple teams be composed for a single project?
Correct
Developers should be self-organized and they’re responsible for teams formations and composition.
Incorrect
Developers should be self-organized and they’re responsible for teams formations and composition.
Question 55 of 80
55. Question
1 points
Are Scrum values.
Correct
The Scrum values named in the Scrum guide are Commitment, Courage, Focus, Openness, Respect. The Scrum Theory Pillars are Transparency, Inspection, Adaptation.
Incorrect
The Scrum values named in the Scrum guide are Commitment, Courage, Focus, Openness, Respect. The Scrum Theory Pillars are Transparency, Inspection, Adaptation.
Question 56 of 80
56. Question
1 points
Are Scrum pillars.
Correct
The Scrum Theory Pillars named in the Scrum guide are Transparency, Inspection, Adaptation. The Scrum values are Commitment, Courage, Focus, Openness, Respect.
Incorrect
The Scrum Theory Pillars named in the Scrum guide are Transparency, Inspection, Adaptation. The Scrum values are Commitment, Courage, Focus, Openness, Respect.
Question 57 of 80
57. Question
1 points
What does it mean for the Development Team to be a Cross-Functional team?
Correct
Cross-Functional means that the professionals in the Team Development should have the all the expertise to do the necessary work in order to deliver a potentially releasable Increment of “Done” product at the end of each Sprint.
Incorrect
Cross-Functional means that the professionals in the Team Development should have the all the expertise to do the necessary work in order to deliver a potentially releasable Increment of “Done” product at the end of each Sprint.
Question 58 of 80
58. Question
1 points
A programmer is not working properly and is blocking the progress of the team and their activities constantly. Who should decide about the future of this person as a member of the team?
Correct
The Development Team is Self-Organized, therefore this is a decision and responsibility of its members. Of course, the Scrum Master must address and support this decision since is also an impediment.
Incorrect
The Development Team is Self-Organized, therefore this is a decision and responsibility of its members. Of course, the Scrum Master must address and support this decision since is also an impediment.
Question 59 of 80
59. Question
1 points
Whose decision is it to establish the tasks to be performed during the Sprint?
Correct
The Development Team is self-organized, hence its members decide on the way they work and on the technical approach of the project.
Incorrect
The Development Team is self-organized, hence its members decide on the way they work and on the technical approach of the project.
Question 60 of 80
60. Question
1 points
At the beginning of the Sprint, the Development Team has neither the tools nor infrastructure needed to complete the current Sprint Backlog Items. What two things the Scrum Master should do?
Correct
Infrastructure and tools are not prepared upfront, because it requires a complete understanding of the whole project and product, which is usually not the case, so we need to hold on to the adaptation pillar. The required infrastructure and tools will be prepared gradually through the project, because they depend on the product we’re going to create, which in turn is defined through the project.
Incorrect
Infrastructure and tools are not prepared upfront, because it requires a complete understanding of the whole project and product, which is usually not the case, so we need to hold on to the adaptation pillar. The required infrastructure and tools will be prepared gradually through the project, because they depend on the product we’re going to create, which in turn is defined through the project.
Question 61 of 80
61. Question
1 points
The Sprint Backlog contains items pulled only from the Product Backlog.
Correct
We can’t change the Sprint Goal, however, the team can talk and negotiate with the Product Owner in order to add new Sprint Backlog Items as needed.
Incorrect
We can’t change the Sprint Goal, however, the team can talk and negotiate with the Product Owner in order to add new Sprint Backlog Items as needed.
Question 62 of 80
62. Question
1 points
The Sprint over when…
Correct
Scrum timeboxed events are not extendable, you can take the available time for some these events as maximum duration, so they can be finished earlier if everything is done, but Sprint timeboxes have a fixed duration, this means they can not shrink. If everything is finished before the end of the Sprint, the Development Team will pick the next item from the Product Backlog and starts working on that.
Incorrect
Scrum timeboxed events are not extendable, you can take the available time for some these events as maximum duration, so they can be finished earlier if everything is done, but Sprint timeboxes have a fixed duration, this means they can not shrink. If everything is finished before the end of the Sprint, the Development Team will pick the next item from the Product Backlog and starts working on that.
Question 63 of 80
63. Question
1 points
The Sprint Backlog includes…
Correct
User Stories, Use Cases, Tests, Tasks and even other elements which help to define and clarify the work can be part of the Sprint Backlog.
Incorrect
User Stories, Use Cases, Tests, Tasks and even other elements which help to define and clarify the work can be part of the Sprint Backlog.
Question 64 of 80
64. Question
1 points
What represents the trend line in a burndown chart, thorough a Sprint?
Correct
The trend line gives us visibility about the forecast for the finishing date, considering a constant development team Capacity for the Sprint Backlog.
Incorrect
The trend line gives us visibility about the forecast for the finishing date, considering a constant development team Capacity for the Sprint Backlog.
Question 65 of 80
65. Question
1 points
What is the best approach when a developer is not working properly?
Correct
The Development Team is responsible about its members because it’s self-organized, this means its member decides about removing any member from the team. Since this situation is actually an impediment, the Scrum Master can help the team.
Incorrect
The Development Team is responsible about its members because it’s self-organized, this means its member decides about removing any member from the team. Since this situation is actually an impediment, the Scrum Master can help the team.
Question 66 of 80
66. Question
1 points
How much time by day, should the Development Team work on their tasks?
Correct
Agile principles support processes which promote sustainable development, this means that every person related directly to a project should be able to maintain a constant pace indefinitely.
Incorrect
Agile principles support processes which promote sustainable development, this means that every person related directly to a project should be able to maintain a constant pace indefinitely.
Question 67 of 80
67. Question
1 points
What is the max time-box duration for a Sprint Planning meeting?
Correct
Sprint Planning is time-boxed to a maximum of eight hours for a one-month Sprint. For shorter Sprints, the event is usually shorter.
Incorrect
Sprint Planning is time-boxed to a maximum of eight hours for a one-month Sprint. For shorter Sprints, the event is usually shorter.
Question 68 of 80
68. Question
1 points
Which two of the following are Scrum Master responsibilities?
Correct
The Scrum Master serves the organization in several ways, including leading and coaching the organization in its Scrum adoption, planning Scrum implementations within the organization, also the Scrum Master serves the Development Team in several ways, including, removing impediments to the Development Team’s progress.
Incorrect
The Scrum Master serves the organization in several ways, including leading and coaching the organization in its Scrum adoption, planning Scrum implementations within the organization, also the Scrum Master serves the Development Team in several ways, including, removing impediments to the Development Team’s progress.
Question 69 of 80
69. Question
1 points
The Sprint Backlog contains only pulled items from Product Backlog.
Correct
Certainly, the Sprint Backlog contains the selected Product Backlog items but also contains the tasks for the current Sprint.
Incorrect
Certainly, the Sprint Backlog contains the selected Product Backlog items but also contains the tasks for the current Sprint.
Question 70 of 80
70. Question
1 points
What is the level of definition needed for the Sprint Backlog through the Sprint Planning?
Correct
The Sprint Planning priority is answering two questions:
What can be delivered in the Increment resulting from the upcoming Sprint?
How will the work needed to deliver the Increment be achieved?
The team doesn’t need to get all the detail about every task as long these questions are answered and the pending definition can be completed as soon as possible in refinement activities.
Incorrect
The Sprint Planning priority is answering two questions:
What can be delivered in the Increment resulting from the upcoming Sprint?
How will the work needed to deliver the Increment be achieved?
The team doesn’t need to get all the detail about every task as long these questions are answered and the pending definition can be completed as soon as possible in refinement activities.
Question 71 of 80
71. Question
1 points
Which two of the following are the result of the Sprint Planning?
Correct
The Sprint Goal and Sprint Backlog are created during the Sprint Planning meeting.
Incorrect
The Sprint Goal and Sprint Backlog are created during the Sprint Planning meeting.
Question 72 of 80
72. Question
1 points
In this event, the Scrum Team and stakeholders talk and collaborate about what was done in the Sprint, in order to share the Sprint progress.
Correct
The Sprint Review event is held at the end of the Sprint to inspect the Increment and adapt the Product Backlog if needed. Attendees also collaborate on the next things that could be done to optimize value.
Incorrect
The Sprint Review event is held at the end of the Sprint to inspect the Increment and adapt the Product Backlog if needed. Attendees also collaborate on the next things that could be done to optimize value.
Question 73 of 80
73. Question
1 points
Choose two purposes of Definition of Done.
Correct
Everyone in the Scrum TEam must understand what “Done” means. Although this may vary significantly per Scrum Team, members must have a shared understanding of what it means for work to be complete, to ensure transparency. This is the definition of “Done” for the Scrum Team and is used to assess when work is complete on the product Increment.
Incorrect
Everyone in the Scrum TEam must understand what “Done” means. Although this may vary significantly per Scrum Team, members must have a shared understanding of what it means for work to be complete, to ensure transparency. This is the definition of “Done” for the Scrum Team and is used to assess when work is complete on the product Increment.
Question 74 of 80
74. Question
1 points
When the Development Team find itself in a situation where doesn’t have the proper tools and infrastructure, what are the best two things to do?
Correct
Sprint Zero doesn´t exist in the Scrum framework and all the Sprints should be able to create an Increment of working software. The Inspections and Adaptation concepts are about making adjustments gradually through the project, this includes infrastructure and tools.
Incorrect
Sprint Zero doesn´t exist in the Scrum framework and all the Sprints should be able to create an Increment of working software. The Inspections and Adaptation concepts are about making adjustments gradually through the project, this includes infrastructure and tools.
Question 75 of 80
75. Question
1 points
Who must express clearly the Product Backlog items?
Correct
The Product Owner owns the Product Backlog and is the sole person responsible for it. The Product Owner does Product Backlog management, this includes:
• Clearly expressing Product Backlog items.
• Ordering the items in the Product Backlog to best achieve goals and missions.
• Optimizing the value of the work the Development Team performs.
• Ensuring that the Product Backlog is visible, transparent, and clear to all, and shows what the Scrum Team will work on next.
• Ensuring the Development Team understands items in the Product Backlog to the level needed.
Incorrect
The Product Owner owns the Product Backlog and is the sole person responsible for it. The Product Owner does Product Backlog management, this includes:
• Clearly expressing Product Backlog items.
• Ordering the items in the Product Backlog to best achieve goals and missions.
• Optimizing the value of the work the Development Team performs.
• Ensuring that the Product Backlog is visible, transparent, and clear to all, and shows what the Scrum Team will work on next.
• Ensuring the Development Team understands items in the Product Backlog to the level needed.
Question 76 of 80
76. Question
1 points
Is at most a four-hour meeting for one-month Sprints.
Correct
The Sprint Review is at most a four-hour meeting for one-month Sprints. For shorter Sprints, the event is usually shorter. During this event, the Scrum Team and stakeholders collaborate about what was done in the Sprint, so is an opportunity for inspection and adaptation.
Incorrect
The Sprint Review is at most a four-hour meeting for one-month Sprints. For shorter Sprints, the event is usually shorter. During this event, the Scrum Team and stakeholders collaborate about what was done in the Sprint, so is an opportunity for inspection and adaptation.
Question 77 of 80
77. Question
1 points
What should do the Scrum Team during the Hardening Sprint
Correct
There’s no such thing as Sprint Hardening Sprint. We have a Sprint 1, Sprint 2 and go on, a surprise additional Sprint or a planned buffer sprint is not in alignment with Agile principles of timeboxed development to create a potentially shippable product. If the stories are correctly prioritized, the Definition of Done is unambiguous, and the product backlog is regularly refined based on business priorities, the teams should be able to complete the development tasks.
Incorrect
There’s no such thing as Sprint Hardening Sprint. We have a Sprint 1, Sprint 2 and go on, a surprise additional Sprint or a planned buffer sprint is not in alignment with Agile principles of timeboxed development to create a potentially shippable product. If the stories are correctly prioritized, the Definition of Done is unambiguous, and the product backlog is regularly refined based on business priorities, the teams should be able to complete the development tasks.
Question 78 of 80
78. Question
1 points
Who is responsible for getting buy-in from stakeholders?
Correct
The Product Owner is responsible for getting buy-in, understanding the stakeholders’ concerns and goals. The Product Owner communicates and represents the desires of the client.
Incorrect
The Product Owner is responsible for getting buy-in, understanding the stakeholders’ concerns and goals. The Product Owner communicates and represents the desires of the client.
Question 79 of 80
79. Question
1 points
What is an important way for the Scrum Master to increase the productivity of the Development Team?
Correct
The Scrum Master serves the Development Team in several ways like:
• Coaching the Development Team in self-organization and cross-functionality.
• Helping the Development Team to create high-value products.
• Removing impediments to the Development Team’s progress.
• Facilitating Scrum events as requested or needed.
• Coaching the Development Team in organizational environments in which Scrum is not yet fully adopted and understood.
Incorrect
The Scrum Master serves the Development Team in several ways like:
• Coaching the Development Team in self-organization and cross-functionality.
• Helping the Development Team to create high-value products.
• Removing impediments to the Development Team’s progress.
• Facilitating Scrum events as requested or needed.
• Coaching the Development Team in organizational environments in which Scrum is not yet fully adopted and understood.
Question 80 of 80
80. Question
1 points
A Scrum Team must have at least one Release Sprint.
Correct
The purpose of all Sprints is to create an Increment of “Done” work, a piece of working software usable and potentially releasable, however team doesnt need realese every Sprint, but eventually, the team must release its work.
Incorrect
The purpose of all Sprints is to create an Increment of “Done” work, a piece of working software usable and potentially releasable, however team doesnt need realese every Sprint, but eventually, the team must release its work.
We want to improve this simulator and create more exam simulators and useful free content for you. If you wish to support this effort you can donate, thank you for helping out: